A new foundation had to be dug for the new Press Brake.
Reinforcing and anchor bolts had to be put in before the concrete was poured.
Pouring the concrete for the foundation.
Concrete foundation poured and left to cure.
New Big Blue Baby arrives on the truck.
It arrived all wrapped against the elements.
Unwrapping it was like unwrapping presents.
It's BIG and shiny and blue!!!
That door seems kinda small.
Mega moving equipment to unload the Big Blue Baby.
Gently lowering it to the surface.
Getting ready to move it inside.
Maneuvering something this big takes finesse.
Big Blue dangles close to it's pad.
Now it is being positioned over the anchor bolts.
Exact placement is necessary to hit the mark.
Placing the last corner properly.
The Big Blue Baby is on it's anchor bolts.
Big Blue anchored down and ready for electrical installation.
It's getting a good waxing and it's electrical parts and inner pieces are being installed.
Big Blue all settled in and working.
This brake can bend long parts. Very cool.